Risk Register Update Template for Trades & Construction

A recurring procedure for reviewing, updating, and maintaining the job risk register to ensure risks are proactively identified, assessed, and mitigated throughout the job lifecycle.

Purpose

To maintain an accurate and current view of job risks so that the job team and stakeholders can make informed decisions and take timely action to prevent or minimise the impact of adverse events.

Scope

Applies to all active job risks from initial identification through to closure, including regular review cycles and event-triggered updates.

Prerequisites

  • Established risk register with an agreed risk assessment framework including probability and impact scales
  • Risk owners assigned for all identified risks
  • Regular risk review cadence defined in the job management plan
Compliance Note

Compliant with Safe Work Australia requirements, state WHS legislation, and Building Code of Australia (NCC) documentation standards.

Step-by-Step Procedure

1

Identify New Risks

Proactively scan the job environment, recent events, and upcoming activities to identify any new risks that should be added to the register.

  • 1.1Review recent job progress reports, site meeting minutes, and change requests for emerging risk indicators
  • 1.2Consult with team members and subject matter experts about potential risks in their areas
  • 1.3Check external factors such as market conditions, regulatory changes, or vendor issues that could affect the job
Project Manager
1 hour
Risk Register, Project Management Software
Tips
  • Use a risk prompt checklist covering common risk categories to ensure comprehensive identification
2

Reassess Existing Risks

Review all open risks in the register to update their probability and impact ratings based on current job conditions and any new information.

  • 2.1For each open risk, evaluate whether the probability has increased, decreased, or remained the same since the last review
  • 2.2Reassess the potential impact considering any changes in job scope, timeline, or dependencies
  • 2.3Recalculate risk scores and reprioritise the risk register accordingly
Project Manager
1-2 hours
Risk Register, Spreadsheet Application
3

Review Mitigation Action Progress

Check the status of all planned risk mitigation actions to ensure they are being executed on schedule and are having the intended effect.

  • 3.1Contact risk owners to obtain status updates on their assigned mitigation actions
  • 3.2Assess whether completed mitigation actions have reduced the risk as expected
  • 3.3Identify any mitigation actions that are overdue or stalled and escalate as needed
  • 3.4Define new or revised mitigation actions where existing plans are insufficient
Project Manager
1-2 hours
Risk Register, Project Management Software
4

Close Resolved Risks

Formally close any risks that have been fully mitigated, are no longer relevant due to changed circumstances, or have occurred and been managed.

  • 4.1Review risks flagged for potential closure and confirm with the risk owner that closure is appropriate
  • 4.2Job card the closure rationale and any residual risk that remains
  • 4.3Move closed risks to the closed section of the register while retaining the full history
Project Manager
30 minutes
Risk Register
5

Escalate Critical Risks

Identify any risks that have reached or exceeded the defined escalation threshold and formally escalate them to the appropriate stakeholders for attention.

  • 5.1Review the updated risk register for any risks that meet the escalation criteria defined in the risk management plan
  • 5.2Prepare an escalation brief for each critical risk including the current assessment, mitigation status, and required stakeholder action
  • 5.3Submit the escalation to the job sponsor or steering committee as appropriate
Project Manager
30 minutes to 1 hour
Risk Register, Email
6

Update and Distribute the Risk Report

Produce an updated risk summary report and distribute it to the job team and stakeholders as part of the regular reporting cycle.

  • 6.1Generate the risk summary showing total open risks, new risks added, risks closed, and top risks by score
  • 6.2Include a trend analysis showing how the risk profile has changed since the last report
  • 6.3Distribute the report to all stakeholders via the agreed communication channel
Project Coordinator
30 minutes to 1 hour
Risk Register, Email, Presentation Software
Tips
  • Use a visual risk heat map to communicate the risk profile at a glance

Quality Checkpoints

All open risks have been reviewed and their assessments updated within the defined review cycle
Every risk has an assigned owner and at least one active mitigation action with a due date
Critical risks site meeting the escalation threshold have been formally escalated to the appropriate authority

Common Mistakes to Avoid

Treating the risk register as a static job card that is only updated at milestone reviews rather than on a regular cadence
Assigning risk ownership but never following up on mitigation action progress, allowing risks to go unmanaged
Failing to close risks that are no longer relevant, resulting in an inflated register that obscures the true risk picture

Expected Outcomes

Risk Register Currency

Percentage of risks that have been reviewed and updated within the defined review cycle, indicating how current the register is

Mitigation Action Completion Rate

Percentage of risk mitigation actions completed on or before their scheduled due date

Risk Materialisation Rate

Percentage of identified risks that materialised into actual issues, measured against the total number of risks identified, indicating identification and mitigation effectiveness

Frequently Asked Questions

Should we include positive risks or opportunities in the register?

Yes, a comprehensive risk register should include opportunities as well as threats. Positive risks represent potential benefits that the team can exploit or enhance. Managing opportunities alongside threats gives stakeholders a balanced view of uncertainty.

How often should the risk register be updated?

For most jobs, a fortnightly review cycle is appropriate. High-risk jobs or those in critical phases may benefit from weekly reviews. The frequency should be defined in the job risk management plan and adjusted based on the job risk profile.

Who is responsible for identifying risks?

Risk identification is a shared responsibility. While the job manager facilitates the process, every team member should be encouraged to raise potential risks. Stakeholders, subject matter experts, and even customers can contribute valuable risk insights.

What is the difference between a risk and an issue?

A risk is an uncertain event that may occur in the future and would affect the job if it does. An issue is a problem that has already occurred and requires immediate action. When a risk materialises, it transitions from the risk register to the issue log.