Back to Project Delivery
Project Delivery
Accounting & Finance
Updated March 2026

Scope Change Request — Accounting & Finance Edition

A controlled procedure for receiving, evaluating, approving, and implementing changes to the agreed engagement scope, ensuring that impacts on schedule, budget, and quality are fully understood before decisions are made.

Purpose

To provide a disciplined approach to managing scope changes so that the engagement maintains its integrity while remaining responsive to legitimate business needs and evolving requirements.

Scope

Covers all changes to the agreed engagement scope from the point of initial request through to implementation and documentation of the approved change.

Prerequisites

  • Approved engagement scope baseline documented in the engagement plan or statement of work
  • Change management process defined and communicated to all stakeholders
  • Change request form or template available in the engagement management system
Compliance Note

Built with ASIC regulatory requirements, AML/CTF compliance, Tax Practitioners Board obligations, and APES standards in mind.

Step-by-Step Procedure

1

Receive and Log the Change Request

Capture the change request from the requester using the standard change request form, ensuring all required information is provided for proper evaluation.

  • 1.1Direct the requester to complete the change request form with a description of the desired change and business justification
  • 1.2Assign a unique change request identifier and log it in the change register
  • 1.3Acknowledge receipt of the change request to the requester within one business day
Project Manager
30 minutes
Project Management Software
2

Perform Initial Screening

Review the change request to determine if it is valid, within the authority of the change process, and warrants a full impact assessment.

  • 2.1Verify the change request is clearly described and has a legitimate business justification
  • 2.2Determine whether the change falls within the engagement scope or is a separate initiative
  • 2.3Classify the change by size and complexity to determine the appropriate approval authority
Project Manager
30 minutes
Project Management Software
Tips
  • Minor changes below a defined threshold may follow an expedited approval path
3

Conduct Impact Assessment

Analyse the change request to determine its impact on the engagement schedule, budget, resources, quality, and risks.

  • 3.1Estimate the additional effort, duration, and cost required to implement the change
  • 3.2Assess the impact on the current engagement schedule including any knock-on effects to downstream tasks
  • 3.3Identify any new risks or quality considerations introduced by the change
  • 3.4Working paper the impact assessment findings in a structured format for decision-makers
Project Manager
2-4 hours
Project Management Software, Spreadsheet Application
4

Present to Change Authority for Decision

Submit the change request with the completed impact assessment to the designated change authority for a formal approve, reject, or defer decision.

  • 4.1Prepare a change decision brief summarising the request, justification, and impact assessment
  • 4.2Present the change request at the next change control client meeting or circulate for asynchronous decision
  • 4.3Record the decision along with any conditions, modifications, or rationale in the change register
Project Manager
1 hour
Project Management Software, Email
5

Communicate the Decision

Notify all relevant stakeholders of the change decision, including the requester, engagement team, and any affected parties.

  • 5.1Inform the requester of the decision and any conditions attached
  • 5.2Notify the engagement team of approved changes and updated expectations
  • 5.3Update the engagement sponsor if the change has significant commercial implications
Project Manager
30 minutes
Email, Communication Platform
6

Implement the Approved Change

Incorporate the approved change into the engagement plan, update the schedule and budget baselines, and assign the work to the appropriate team members.

  • 6.1Update the engagement scope working paper and work breakdown structure to reflect the change
  • 6.2Adjust the engagement schedule and budget to incorporate the approved change impact
  • 6.3Assign new tasks to team members and update resource allocations as needed
Project Manager
1-2 hours
Project Management Software
Tips
  • Save a new schedule version noting the change request identifier for traceability
7

Update the Change Register

Close the change request in the change register with the final decision, implementation date, and any lessons learned for future reference.

  • 7.1Record the final status of the change request as approved, rejected, or deferred
  • 7.2Note the implementation date and any variances from the original impact assessment
  • 7.3Archive the change request documentation for engagement audit purposes
Project Coordinator
15 minutes
Project Management Software

Quality Checkpoints

Every change request has a unique identifier and is logged in the change register before evaluation begins
Impact assessment covers schedule, budget, resource, quality, and risk dimensions before the decision is made
The change authority decision is formally documented with rationale and any conditions
Approved changes are reflected in the updated engagement plan, schedule, and budget baselines

Common Mistakes to Avoid

Accepting verbal scope changes without requiring them to go through the formal change request process
Performing incomplete impact assessments that only consider schedule without evaluating budget and risk implications
Implementing changes before obtaining formal approval from the designated change authority
Failing to update the engagement baselines after a change is approved, making future variance analysis inaccurate

Expected Outcomes

Change Request Cycle Time

Average number of business days from change request submission to formal decision, measuring the responsiveness of the change management process

Scope Creep Index

Number of uncontrolled scope changes detected versus the total number of formal change requests processed, indicating the effectiveness of the change control process

Frequently Asked Questions

Can the engagement manager approve scope changes independently?

Most organisations grant the engagement manager authority to approve minor changes below a defined threshold of cost and schedule impact. Larger changes require approval from the engagement sponsor, steering committee, or client depending on the contractual arrangement.

Should the client be charged for change requests?

This depends on the contract terms. Fixed-price contracts typically require commercial negotiation for scope changes. Time-and-materials contracts may absorb changes within the ongoing billing arrangement. Always refer to the contract before committing to any commercial impact.

What constitutes a scope change versus a refinement of existing requirements?

A scope change introduces new deliverables, removes planned deliverables, or significantly alters the agreed functionality or specifications. A refinement clarifies how existing agreed deliverables will be implemented without changing what is delivered. When in doubt, log it as a change request for formal evaluation.

How should we handle urgent change requests that cannot wait for the next change control client meeting?

Establish an expedited approval process for urgent changes. The engagement manager can seek verbal approval from the change authority with a commitment to ratify the decision at the next formal client meeting. Working paper the urgency and the verbal approval in the change register.

What happens if a change request is rejected but the requester disagrees?

The requester can appeal the decision to the next level of authority, typically the steering committee or engagement board. The appeal should include additional justification or new information that was not considered in the original assessment.

Want this customised for YOUR business?

We'll tailor every step to your exact operations, tools, and team structure.